Google revives Iowa nuclear plant for AI power. Tech giant partners with NextEra to restart Duane Arnold reactor by 2029, securing 615 MW of carbon-free electricity

Google revives Iowa nuclear plant for AI power

Google announced a groundbreaking 25-year deal to restart Iowa's shuttered Duane Arnold nuclear reactor by 2029, partnering with NextEra Energy to secure 615 megawatts of zero-carbon power for its data centers. The move reflects Big Tech's urgent hunt for reliable electricity as AI workloads explode, with reactor restarts offering faster capacity than new construction.

30 October 2025

News

banner

TLDR:

  • Google to restart Duane Arnold nuclear reactor by 2029, securing 615 MW of zero-carbon power for data centers
  • Tech companies driving massive clean-energy deals, with 17 GW contracted in 2024 to support AI power needs
  • Reactor restart offers faster path to power capacity compared to new nuclear plant construction

Google will restart Iowa's shuttered Duane Arnold nuclear reactor by 2029, partnering with NextEra Energy to secure 615 megawatts of zero-carbon power for its data centers in a 25-year deal.

Driving the news: The tech giant announced the revival plan on October 27–28, 2025, marking the latest move by Big Tech to lock down reliable, carbon-free electricity as AI workloads explode.

Why it matters: Data center companies contracted more than 17 GW of clean-energy deals in 2024, accounting for roughly 60% of corporate clean-energy deals in the United States. Nuclear restarts offer a faster path to massive power capacity than building new plants from scratch.

The backstory: The Duane Arnold Energy Center went dark in 2020 after a summer derecho damaged its secondary containment system—the safeguard preventing radioactive gas releases. NextEra has been hunting for a restart partner ever since.

By the numbers:

  • 615 MW total capacity (601 MW original, plus 14 MW from upgrades)
  • Google gets majority of output; Central Iowa Power Cooperative takes the rest
  • 2029 target restart date
  • Neither company disclosed financial terms

The big picture: This isn't a one-off. Microsoft struck a 20-year deal with Constellation Energy in September 2024 to restart Three Mile Island's Unit 1 reactor by 2028—a $1.6 billion project delivering 835 MW. Michigan's Palisades plant is also targeting a late 2025–2026 restart after securing DOE loan support and NRC approvals earlier this year.

Between the lines: Reactor restarts shave years off timelines compared to new nuclear construction, but they're still years-long projects requiring multiple NRC licensing changes, state permits, and major equipment overhauls. That puts them in competition with natural gas plants, which also take years to develop.

Reality check: While Google waits for nuclear, it's also deploying solar and batteries—which can come online in months, not years. For America, this means a multi-pronged approach to powering the AI revolution.

What's next: NextEra must secure NRC approvals and navigate multi-year equipment deliveries before the 2029 target becomes reality. The company also plans to buy out minority stakeholders, including the Central Iowa Power Cooperative's 20% stake.

The bottom line: Tech's hunger for electricity is breathing new life into America's dormant nuclear fleet—but the 2029 timeline is conditional on clearing regulatory hurdles that have tripped up similar projects before.